1. Set the acceptance basis before the test
Start with the signed technical specification, approved drawings, quotation scope and control description. List each supplied item and identify interfaces or exclusions, including veneer lay-up, pre-press, hot press, loading and unloading equipment, conveyors, stacking, heating connections and mill utilities. A FAT cannot verify equipment that is outside the agreed supply boundary.
Create a test protocol that states the test method, instruments, sample size, operating mode, acceptance limit and responsible witness for every check. Enter limits from the contract or obtain written agreement before testing; do not substitute an assumed value. Identify documents and calibration evidence required for measuring instruments. Mark any item still awaiting agreement as “To confirm.”
| Test area | Evidence to define | Decision basis |
|---|---|---|
| Scope and build | Equipment list, drawings, nameplates | Matches approved scope or logged deviation |
| Mechanical operation | Movement checks and clearances | Agreed sequence completes without interference |
| Controls and interlocks | I/O list, alarms, safety logic | Specified functions respond as documented |
| Heating and pressure | Test method and readings | Contractual limits and method are met |
| Panel trial | Material, recipe owner, sample plan | Agreed sample criteria are recorded |
| Documentation | Manuals, diagrams, open-item list | Required documents delivered or tracked |
2. Inspect the assembled line and interfaces
Compare the installed assembly with approved general-arrangement and interface drawings. Check press frame and platen identification, opening arrangement, loading access, guarding, hydraulic and electrical connections, pipework, cable routing and maintenance access. Record discrepancies with a location, photograph reference, drawing revision and disposition; a visual inspection alone does not establish structural adequacy.
For an automated line, inspect transfer points from lay-up or batch preparation through loading, pressing, unloading and stacking, but test only the equipment included in the order. Confirm that the declared product dimensions, veneer lay-up arrangement and handling aids are represented in the test plan. Veneer plies and press openings are different quantities: openings describe press levels, while plies describe layers in a panel.
3. Run functional and control tests
Exercise each operating mode agreed for the FAT, including manual or setup operation and automatic sequences where supplied. Observe opening and closing, loader insertion and withdrawal, batch transfer, unloader movement, conveyor starts and stops, and stack handling. Confirm that the sequence cannot advance when a required permissive is absent, using the approved control narrative and test cases.
Test alarms, emergency-stop circuits, guards, position feedback and recovery after a controlled interruption according to the supplier’s documented procedure. Record the initiating condition, expected response and observed response. Do not treat a screen indication as proof of a physical function; observe the relevant device or movement. Safety acceptance limits and validation responsibilities must come from the project documents and qualified parties, not be invented for this checklist.
4. Verify process performance without overclaiming
Where a hot functional trial is included, agree beforehand which materials, lay-up, adhesive system, panel format and operating settings will be used, and who supplies or approves them. These process inputs are mill- and product-specific; the FAT should not invent an adhesive recipe or temperature. Record the actual conditions, press cycle definition, loading pattern, measurements and sample identification so results can be interpreted in context.
For a pressure or heating check, agree the measurement locations, instrument method, stabilization approach and contractual acceptance limits in advance. A displayed setpoint is not the same as an independently verified platen condition. Where the factory cannot reproduce site utilities or production materials, document the limitation and move the affected performance verification to site acceptance rather than declaring it passed.
5. Close findings and decide release status
Classify each result as pass, fail, not tested or conditional, with supporting evidence. Give every deviation an owner, due date, corrective action and retest requirement. Distinguish shipment-critical nonconformities from agreed outstanding documentation or site-dependent tests, using the contract’s release rules. A signed FAT record should identify attendees, test dates, equipment configuration, software revision and any conditions attached to release.
The FAT decision is limited to the tested configuration and conditions. It does not by itself prove production capacity, long-term reliability, finished-panel compliance or successful installation at the mill. Site acceptance should separately cover foundations and utilities, integration with mill equipment, operator training where contracted, and performance under agreed production conditions. We help mills organize the specification and sourcing requirements; test execution and acceptance responsibilities should be explicit in the supply agreement.
Questions about this configuration
Does passing a FAT prove the line will meet the mill’s output target?
Not on its own. A FAT demonstrates only the functions and performance criteria tested under recorded factory conditions. Output at the mill depends on the agreed cycle definition, loading pattern, materials, utilities, staffing, downstream capacity and other site conditions; verify production performance separately under a defined site acceptance test.
Should the FAT include finished plywood testing?
Only if the contract defines a representative trial, inputs, sample plan, measurement methods and pass criteria. If suitable veneer, adhesive, utilities or process conditions are unavailable at the factory, record the limitation and agree a site trial instead. Do not infer product compliance from an unstructured demonstration.
What should happen if a test cannot be completed before shipment?
Record it as not tested or conditional, state why, identify the responsible party and agree the evidence, deadline and retest location. Apply the contract’s shipment-release provisions. Do not mark an unperformed test as passed.