Take the right project data
to the next conversation.
Engineering, production, maintenance and purchasing teams preparing a press-line project.
Information to collect
- platen size
- openings
- pitch
- entry datum
- clearance
- cylinders/force
- heating interfaces
- PLC
- floor/ceiling
- shutdown
- photo positions
What to record
Start with the press identification and basic arrangement: manufacturer or model if known, number of openings, platen dimensions, daylight pitch and available opening height. Record whether dimensions refer to the platen, loaded panel or finished panel. Openings describe the press; veneer plies describe the lay-up and are not interchangeable.
Measure the approach and discharge sides, floor-to-platen height, nearby columns, walls, pits and obstructions. Include the usable space for loading and unloading equipment, not just the footprint of the press.
| Measurement | Record | Unit or note |
|---|---|---|
| Platen length and width | Measured working surface | mm; identify measurement edges |
| Opening count and pitch | Openings and spacing | Count; mm between reference points |
| Access clearance | Approach and discharge space | mm; note fixed obstructions |
| Press cycle | Loading-to-unloading interval | minutes; state what is included |
Measure consistently
Use a consistent datum and record where each dimension begins and ends. For clearances, capture the narrowest usable passage and note rails, guards, pipes or other items that could restrict equipment travel. Mark uncertain or inaccessible dimensions as To confirm rather than treating them as verified.
Capture operating conditions
Describe how panels enter and leave each opening, the current loading method, and any batch or transfer steps. Record a representative complete cycle and specify whether loading, closing, pressing, opening, unloading and reset or travel are included. This avoids counting handling time twice in a later capacity estimate.
For controls review, note available electrical drawings, PLC details, signals, interlocks and operator stations. Do not infer compatibility from a controller name alone; interfaces and sequence behavior need confirmation.
Use the sheet for preliminary review
A completed sheet supports discussion of access, handling concept and information still needed. It is not a fit approval, safety assessment or performance guarantee. We help plywood mills specify and source equipment; final dimensions, interfaces and configuration require engineering confirmation against the actual press and site.
Questions about this configuration
Should I include every press opening?
Yes. Record the total opening count and, where geometry varies, measure representative openings and identify the differences. Confirm unusual or obstructed openings separately.
Can I estimate dimensions from a drawing?
Use drawings as a reference, but label values taken from drawings and verify critical clearances on site. Mark unverified entries To confirm.
Does completing the sheet confirm a retrofit will fit?
No. It provides inputs for a preliminary review. Equipment fit, press interfaces, operating sequence and site constraints require engineering confirmation.